Year | Operation Name | Number | Type | Opening | District | City | County | Company Name | Railroad Shipments (tons) | Railroad to Mine | Truck Shipments (tons) | Total Production (tons) | Days Worked | Employees | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1964 | Pigeon Creek | Mine | 11 | Mildred 2 | Sullivan | J. & K. Coal Co. | 0 | 0 | 303 | 46 | 2 | Coal prepared at Booth Breaker. | |||
1965 | Pigeon Creek | Mine | 10 | Mildred 2 | Sullivan | J. & K. Coal Co. | 0 | 0 | 608 | 139 | 2 | Abandoned during 1965. Coal prepared at Booth Cleaning Plant. |
Note 2: From a list of Anthracite Operators. This may not be the operation location.