Year | Operation Name | Number | Type | Opening | District | City | County | Company Name | Railroad Shipments (tons) | Railroad to Mine | Truck Shipments (tons) | Total Production (tons) | Days Worked | Employees | Notes |
---|
1894 | Kidder | | Colliery | | 4 | Wilkes-Barre | Luzerne | Kidder Coal Co. | 43,911 | | 0 | 46,844 | 249 | 21 | |
1895 | Kidder | | Colliery | | 4 | Wilkes-Barre | Luzerne | Kidder Coal Co. | 35,622 | | 0 | 38,622 | 179 | 22 | |
1896 | Kidder | | Washery | | 4 | Wilkes-Barre | Luzerne | Kidder Coal Co. | 44,985 | | 0 | 47,985 | 202 | 21 | |
1940 | Kidder | | Mine | | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 0 | | 0 | 0 | | | |
1942 | Kidder | | Mine | Slope | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 135,339 | | 0 | 145,798 | 242 | 250 | Run of mine coal. Prepared at Huber Breaker, 13th District. |
1944 | Kidder | | Colliery | Slope | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 151,039 | | 0 | 169,033 | 311 | 127 | |
1945 | Kidder | | Mine | Slope | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 104,315 | | 0 | 116,593 | 281 | 167 | |
1946 | Kidder | | Mine | Slope | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 132,305 | | 0 | 144,649 | 289 | 209 | Coal prepared at Huber Breaker. |
1947 | Kidder | | Mine | Slope | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 164,790 | | 0 | 180,785 | 295 | 295 | Coal prepared at Huber Breaker. |
1948 | Kidder | | Mine | | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 205,747 | | 0 | 223,560 | 288 | 346 | Coal prepared at Huber Breaker. |
1948 | Kidder | | Stripping | | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 71,245 | | 0 | 77,742 | 239 | 29 | Coal prepared at Huber Breaker. |
1949 | Kidder | | Mine | Slope | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 150,058 | | 0 | 156,081 | 211 | 406 | Coal prepared at Huber Breaker. |
1949 | Kidder | | Stripping | | 11 | Wilkes-Barre 1 | Luzerne | Glen Alden Coal Co. | 31,178 | | 0 | 32,593 | 117 | 15 | Coal prepared at Huber Breaker. |
1959 | Kidder | | Stripping | | 11 | Wilkes-Barre 1 | Luzerne | Number One Contracting Co. | 77,628 | | 40,638 | 164,558 | 182 | 60 | Coal prepared at Harry E. Breaker. |
1960 | Kidder | | Stripping | | 11 | Wilkes-Barre | Luzerne | Number One Contracting Co. | 141,210 | | 88,228 | 335,938 | 294 | 117 | Coal prepared at Harry E. Breaker. |
1961 | Kidder | | Stripping | | 11 | Wilkes-Barre | Luzerne | Number One Contracting Co. | 96,928 | | 87,678 | 230,758 | 298 | 92 | Coal prepared at Harry E. and Dorrance breakers. |
1962 | Kidder | | Stripping | | 11 | Wilkes-Barre | Luzerne | Lehigh Valley Anthracite, Inc. | 69,671 | | 45,623 | 144,606 | 293 | 53 | Coal prepared at Dorrance Breaker. |
1963 | Kidder-Baltimore | | Stripping | | 11 | Wilkes-Barre | Luzerne | Lehigh Valley Anthracite, Inc. | 119,816 | | 63,894 | 214,664 | 330 | 55 | Coal prepared at Harry E. and Dorrance breakers. |
1964 | Kidder-Baltimore | | Stripping | | 11 | Wilkes-Barre | Luzerne | Lehigh Valley Anthracite, Inc. | 110,660 | | 70,075 | 225,720 | 343 | 72 | Coal prepared at Dorrance Breaker. |
1968 | Kidder | | Bank | | 5 | Wilkes-Barre | Luzerne | Lehigh Valley Anthracite, Inc. | 697 | | 629 | 1,704 | 0 | 0 | Coal prepared at Jeddo No. 7 and Harry E. breakers. |
Note 1: Added, does not appear in the mine inspection report.