YearOperation NameNumberTypeOpeningDistrictCityCountyCompany NameRailroad Shipments (tons)Railroad to MineTruck Shipments (tons)Total Production (tons)Days WorkedEmployeesNotes
1938Triad Mine2 LackawannaTriad Coal Co.0Truck 12,6402,6408712 
1939Triad Mine2 LackawannaTriad Coal Co.3,3826,71110,09314422 
1940Triad Mine2 LackawannaTriad Coal Co.7,6906,98114,67117025Run of mine coal prepared at various breakers.
1941Triad Mine2 LackawannaTriad Coal Co.8,5391,93510,47415615 
1942Triad Mine2 LackawannaTriad Coal Co.3,4621823,64412613 
1943G&F MineSlope 12 LackawannaG. & F. Coal Co.2,7604873,2472678Formerly Triad Mine.
1944G&F MineSlope2 LackawannaG. & F. Coal Co.4,7558395,59429410 
1945G&F MineSlope2 LackawannaG. & F. Coal Co.3,7591,9365,69525513Run of mine coal.
1946G&F Mine2Jessup 2LackawannaG. & F. Coal Co.8,8719869,85727310Coal prepared at Moosic Mountain Breaker.

Note 1: Added, does not appear in the mine inspection report.

Note 2: From a list of Anthracite Operators. This may not be the operation location.