BackHomeExport
B&D
Select column header to sort. Hyperlinked items will open a new window.
YearOperation NameNumberTypeOpeningDistrictCityCountyCompany NameRailroad Shipments (tons)Railroad to MineTruck Shipments (tons)Total Production (tons)Days WorkedEmployeesNotes
1937B&D Mine2 LackawannaB. & D. Stone Coal Co.1,4401,5003,64025019 
1938B&D Mine2 LackawannaB. & D. Stone Coal Co.0Truck 12,7252,7258025 
1939B&D Mine1 LackawannaB. & D. Coal Co.9,0292,85111,88021344Formerly Powderly No. 1 Tunnel.
1940B&D Mine1 LackawannaB. & D. Coal Co.19,5037,06326,56627876Run of mine coal prepared at B. & D. Breaker, 2nd District.
1941B&D Mine1 LackawannaB. & D. Coal Co.9,9983,36315,61127544Run of mine coal.
1941B&D Colliery2 LackawannaB. & D. Coal Co.00021611Preparation only.
1942B&D Mine1 LackawannaB. & D. Coal Co.8,84808,84822025 
1942B&D Colliery2 LackawannaB. & D. Coal Co.00021914Preparation only.
1943B&D Mine1 LackawannaB. & D. Coal Co.15,85725,03841,19529751 
1944B&D Stone Mine1 LackawannaB. & D. Coal Co.9,78521,80732,85131135 
1945B&D Stone Mine1 LackawannaB. & D. Coal Co.2,39109,86628126 
1946B&D Stone Breaker1 LackawannaB. & D. Coal Co.6,77507,07529115Stripping coal.
1947B&D Stone Breaker1 LackawannaB. & D. Coal Co.0Truck 17,2497,24913819Stripping coal.

Note 1: Added, does not appear in the mine inspection report.